Aqaba New Liquefied Natural Gas (LNG) Terminal - Jordan

Together with its sister company BAM Contractors from Ireland and its Jordanian joint-venture partner MAG Engineering & Contracting Co. BAM International was awarded the Engineering, Procurement and Construction (EPC) of the LNG jetty in November 2013. BAM Infraconsult was involved in the designing of the civil works. 

The scope of work for the new LNG jetty included a 100 metres trestle on steel piles, a concrete off-loading platform of 20 x 20 metres, four mooring dolphins and four breasting dolphins. The project further comprise a 700-metres long gas pipeline to the shore tie-in point, as well as associated control equipment and instrumentation. The development of the terminal area including roads and two buildings also belonged to the contract.

The terminal was handed over to Aqaba Development Corporation (ADC) in June 2015.