Sefwi Wiawso – Benkyema junction road rehabilitation - Ghana
|
Rehabilitation of 45 kilometres of road, including road widening, earth works, sub-base and crushed stone base layer with double surface dressing finishing, reflective road marking and sign posts. Also included in the project were the construction of earth drains, concrete culverts, stone pitched drains and town drainage. Across the river Sui a bridge spanning 20 metres was constructed using pre-stressed concrete girders and sheet pile abutments.
After completion, improved road conditions reduced travelling time from Sefwi-Wiawso to the Benkyema junction from about 4 hours to 35 minutes.
‘The road is now a first-class one by all standards.’
|
![]() |
![]() Part of the road in July 2006 |
![]() Same part of the road in October 2008 |
Search
Links
- View magazine now also available as iPad App
- View - client magazine BAM International
- BAM press releases
- Royal BAM Group
Enlarge readability
A
A
A